CO129-351 - Public Offices - 1908 — Page 265

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

Mines.

The only mines actually being worked at present are those at Fushun; others are in course of inspection.

Enterprises.-Working of various Railways.

When the railway was taken over, the old system was maintained till the Company had so far perfected its organization as to permit of the introduction of improvements. The actual period of working under the Company was from the 1st April to the 31st September, that is, 183 days. During the period under review the mileage open to traffic, including that carried on on the five miles between Changchun and Menchiatun, was 514 m. 14 ch.; on the Mukden-Antung line, 188 m. 56 ch.

The mileage covered by trains on the main line during this period reaches a total of 1,165,665 miles; on the Mukden-Antung line of 145,527 miles.


Passengers numbered 704,300, and the amount received in fares came to 174,833, the busiest periods being April and May, the slackest June and July. The latter are apparently two months during which little travelling is ever done, and in this particular year matters have been made worse by the heavy floods, which in many places caused all communication to be cut off.

Merchandize.

The amount carried was as follows:--

Tons £ Ordinary merchandize 11,544 228,715 Full-car loads 468,411 Total 479,955

Page 7

The following Table shows the chief restoration work carried out to make good the damage done:-

Embankments repaired 2,997 tsubo Bridges, parapets, &c., repaired 227 Bridges and accessories repaired in 48 localities Track repaired 28 chains débris cleared 36 tsubo

This does not include ordinary repairs for the maintenance of the line. On the Antung-Mukden line maintenance of the track is an arduous task. This road was built hastily during the war for military purposes. It runs, too, through a difficult and inaccessible country full of steep gradients, while the bridges, which number 450, are only temporary structures, which, since the three years they have been standing, have for the most part become rotten. Nor are matters made easier by the frequently recurring floods, particularly those of the last summer. For instance, the bridges and embankments north of Pensihu were destroyed in this way on the 12th June last. Scarcely was the work of repairing completed, when two days of heavy rain in August, causing the rivers to rise from twelve to seventeen feet, undid all the work done; twenty-seven bridges were washed away, and almost incalculable damage done to earthworks, culverts, &c. The result was suspension of traffic for some time, for, notwithstanding the energetic manner in which repairs were pushed forward, it was not till the last day of September that the whole line was free again.

The following Table gives statistics of the work done to repair damages of this kind:

Embankments, &c., repaired 680 tsubo Bridges (temporary) repaired, Culverts repaired 3,723 feet Covered drains repaired 3 places Track débris cleared 13 chains relayed 242 tsubo 1 m, 32 ch

Freight charges

The principal articles transported were as follows:-

Classification Quantity Classification Quantity Tons Tons Rice 9,685 Flour 6,661 Wheat 1,086 Beans 47,458 Bean-cake 2,862 Tobacco 1,040 Miscellaneous cereals 22,718 Paper 1,767 Salt 13,760 Lime 3,360 Sake 4,186 Dyes and chemicals 1,137 Cotton yarn 837 Cars and their materials 1,875 Silk and cotton tissues 7,335 Lumber 22,039 Earthenware 1,058 Marine products 2,969 Copper and iron goods 8,872 Provisions 3,415 Firewood 1,152 Bones (cattle) 1,024 Kerosene 1,607 Stone materials 8,574 Coal 47,618 Building materials 91,518 Fruit and vegetables 3,950 Rails 4,756 Sugar 3,010 Sleepers 15,510

There were taken over with the railway 302 locomotives, 145 passenger cars, and 4,476 goods cars, making a total of 4,923.

There are at present in the Company's possession 307 locomotives, 289 passenger cars, and 4,507 goods cars, making a total of 5,103.

Details are as follows:-

Main Line Taken over in April Now in existence Increase or Decrease Locomotives- Narrow gauge 6-wheeled tank, B 6 30 8-wheeled tender, F 2 30 Total 220 Broad gauge- American A 10-wheeler F 190 217 3 Consolidation H 422 +++ Total 8 +2 Passenger cars- Special bogie 3 8 +8 2nd class 128 2 3rd class 100 100 +100 4th class 259 +114 Mail cars 12 12 Water tenders 10 15 +13

Maintenance of the Line.

Considerable damage was done to the line during the past summer owing to the unusually heavy rains and to the floods therefrom resulting. In particular, on the 17th July, bridges, embankments, &c., were swept away in numbers, and for a short time communications were suspended. Again, during the heavy floods after the extraordinary rains on the 5th August, two bridges over the Fuchow River were destroyed, and parts of the neighbouring embankment swept away. On the 17th of the same month another flood took place, destroying the work but recently repaired. On this occasion the line was not restored till the 27th of the month. Altogether train traffic was suspended for twenty-one days.

Page 8

(To be continued)

Edit History

2026-06-06 04:10:02 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Mines. The only mines actually being worked at present are those at Fushun; others are in course of inspection. Enterprises.-Working of various Railways. When the railway was taken over, the old system was maintained till the Company had so far perfected its organization as to permit of the introduction of improvements. The actual period of working under the Company was from the 1st April to the 31st September, that is, 183 days. During the period under review the mileage open to traffic, including that carried on on the five miles between Changchun and Menchiatun, was 514 m. 14 ch.; on the Mukden-Antung line, 188 m. 56 ch. The mileage covered by trains on the main line during this period reaches a total of 1,165,665 miles; on the Mukden-Antung line of 145,527 miles. Passengers numbered 704,300, and the amount received in fares came to 174,833, the busiest periods being April and May, the slackest June and July. The latter are apparently two months during which little travelling is ever done, and in this particular year matters have been made worse by the heavy floods, which in many places caused all communication to be cut off. Merchandize. The amount carried was as follows:-- Tons £ Ordinary merchandize 11,544 228,715 Full-car loads 468,411 Total 479,955 Page 7 The following Table shows the chief restoration work carried out to make good the damage done:- Embankments repaired 2,997 tsubo Bridges, parapets, &c., repaired 227 Bridges and accessories repaired in 48 localities Track repaired 28 chains débris cleared 36 tsubo This does not include ordinary repairs for the maintenance of the line. On the Antung-Mukden line maintenance of the track is an arduous task. This road was built hastily during the war for military purposes. It runs, too, through a difficult and inaccessible country full of steep gradients, while the bridges, which number 450, are only temporary structures, which, since the three years they have been standing, have for the most part become rotten. Nor are matters made easier by the frequently recurring floods, particularly those of the last summer. For instance, the bridges and embankments north of Pensihu were destroyed in this way on the 12th June last. Scarcely was the work of repairing completed, when two days of heavy rain in August, causing the rivers to rise from twelve to seventeen feet, undid all the work done; twenty-seven bridges were washed away, and almost incalculable damage done to earthworks, culverts, &c. The result was suspension of traffic for some time, for, notwithstanding the energetic manner in which repairs were pushed forward, it was not till the last day of September that the whole line was free again. The following Table gives statistics of the work done to repair damages of this kind: Embankments, &c., repaired 680 tsubo Bridges (temporary) repaired, Culverts repaired 3,723 feet Covered drains repaired 3 places Track débris cleared 13 chains relayed 242 tsubo 1 m, 32 ch Freight charges The principal articles transported were as follows:- Classification Quantity Classification Quantity Tons Tons Rice 9,685 Flour 6,661 Wheat 1,086 Beans 47,458 Bean-cake 2,862 Tobacco 1,040 Miscellaneous cereals 22,718 Paper 1,767 Salt 13,760 Lime 3,360 Sake 4,186 Dyes and chemicals 1,137 Cotton yarn 837 Cars and their materials 1,875 Silk and cotton tissues 7,335 Lumber 22,039 Earthenware 1,058 Marine products 2,969 Copper and iron goods 8,872 Provisions 3,415 Firewood 1,152 Bones (cattle) 1,024 Kerosene 1,607 Stone materials 8,574 Coal 47,618 Building materials 91,518 Fruit and vegetables 3,950 Rails 4,756 Sugar 3,010 Sleepers 15,510 There were taken over with the railway 302 locomotives, 145 passenger cars, and 4,476 goods cars, making a total of 4,923. There are at present in the Company's possession 307 locomotives, 289 passenger cars, and 4,507 goods cars, making a total of 5,103. Details are as follows:- Main Line Taken over in April Now in existence Increase or Decrease Locomotives- Narrow gauge 6-wheeled tank, B 6 30 8-wheeled tender, F 2 30 Total 220 Broad gauge- American A 10-wheeler F 190 217 3 Consolidation H 422 +++ Total 8 +2 Passenger cars- Special bogie 3 8 +8 2nd class 128 2 3rd class 100 100 +100 4th class 259 +114 Mail cars 12 12 Water tenders 10 15 +13 Maintenance of the Line. Considerable damage was done to the line during the past summer owing to the unusually heavy rains and to the floods therefrom resulting. In particular, on the 17th July, bridges, embankments, &c., were swept away in numbers, and for a short time communications were suspended. Again, during the heavy floods after the extraordinary rains on the 5th August, two bridges over the Fuchow River were destroyed, and parts of the neighbouring embankment swept away. On the 17th of the same month another flood took place, destroying the work but recently repaired. On this occasion the line was not restored till the 27th of the month. Altogether train traffic was suspended for twenty-one days. Page 8 (To be continued)
Baseline (Original)
6 Mines. The only mines actually being worked at present are those at Fushun; others are in course of inspection. Enterprises.-Working of various Railways. When the railway was taken over, the old system was maintained till the Company had so far perfected its organization as to permit of the introduction of improvements. The actual period of working under the Company was from the 1st April to the 31st September, that is, 183 days. During the period under review the mileage open to traffic, including that carried on on the five miles between Changchun and Menchiatun, was 514 m. 14 ch.; on the Mukden-Antung line, 188 m. 56 ch. The mileage covered by trains on the main line during this period reaches a total of 1,165,665 miles; on the Mukden-Antung line of 145,527 miles. to Passengers numbered 704,300, and the amount received in fares came 174,833, the busiest periods being April and May, the slackest June and July. The latter are apparently two months during which little travelling is ever done, aud in this particular year matters have been made worse by the heavy floods, which in many places caused all communication to be cut off. Merchandize. The amount carried was as follows :-- Ordinary merchandize Full-car loads Total Tons. 11,544 468,411 479,955 £ 228,715 } 7 The following Table shows the chief restoration work carried out to make good the damage done :- Embankments repaired Bridges, parapets, &c., repaired Bridges and accessories repaired în Track repaired débris cleared -- 2.997 tsubo," 227 48 localities. 28 chains. 36 teubo." This does not include ordinary repairs for the maintenance of the line. On the Antung-Mukden line maintenance of the track is an arduous task. This road was built hastily during the war for military purposes. It runs, too, through a difficult and inaccessible country full of steep gradients, while the bridges, which number 450, are only temporary structures, which, since the three years they have been standing, have for the most part become rotten. Nor are matters made easier by the frequently recurring floods, particularly those of the last summer. For instance, the bridges and embankments north of Pensihu were destroyed in this way on the 12th June last. Scarcely was the work of repairing completed, when two days of heavy rain in August, causing the rivers to rise from twelve to seventeen feet, undid all the work doue; twenty-seven bridges were washed away, and almost incalculable damage done to earthworks, culverts, &c. The result was suspension of traffic for some time, for, notwithstanding the energetic manner in which repairs were pushed forward, it was not till the last day of September that the whole line was free again. The following Table gives statistics of the work done to repair damages of this kind: Embankments, &c., repaired Bridges (temporary) repaired, Culverts repaired Covered drains repaired Track débris cleared relaid " Curs (in existence). 680 tsubo." 3,723 feet. 3 places. 13 chains. 242 "tsubo." 1 m, 32 ch. Freight charges The principal articles transported were as follows :- Classification. Quantity. Classification. Quantity. Tons, Tons. Rice 9,685 Flour 6,661 Wheat 1,086 Beans 47,458 Bean-cake 2,862 Tobacco 1,040 Miscellaneous cereals 22,718 Paper 1,767 Salt 13,760 Limc 3,360 Sake 4,186 Dyes and chemicals 1,137 Cotton yarn 837 Cars and their materials 1,875 Silk and cotton tissues 7,335 Lumber 22,039 Earthenware 1,058 Marine products 2,969 Copper and iron goods 8,872 Provisions 3,415 Firewood 1,152 Bones (cattle) 1,024 Kerosene 1,607 Stone materials 8,574 Coal 47,618 Building materials 91,518 Fruit and vegetables 3,950 Rails 4,756 Sugar 3,010 Sleepers 15,510 There were taken over with the railway 302 locomotives, 145 passenger cars, and 4,476 goods cars, making a total of 4,923. There are at present in the Company's possession 307 locomotives, 289 passenger cars, and 4,507 goods cars, making a total of 5,103. Details are as follows:- Main Line. Classification. Taken over in April. Now in existence. Increase or Decrease. Locomotives- Narrow gauge 6-wheeled tank, B 6 S-wheeled tender, F 2 Total Broad guage-e American A 10-wheeler F :: 190 30 187 30 220 217 3 Consolidation H 422 +++ སྐ༥༤༣ Total 8 + 2 8 Passenger cars- Special bogie 3 + 8 2nd class 130 Total 145 Water tenders 10 :འ:སྐྲ 15 28 +.13 128 2 100 + 100 259 +114 12 12 : 10 Maintenance of the Line. Considerable damage was done to the line during the past summer owing to the unusually heavy rains and to the floods therefrom resulting. In particular, on the 17th July, bridges, embankments, &c., were swept away in numbers, and for a short time communications were suspended. Again, during the heavy floods after the extraordinary rains on the 5th August, two bridges over the Fuchow River were destroyed, and parts of the neighbouring embankment swept away. On the 17th of the same month another flood took place, destroying the work but recently repaired. On this occasion the line was not restored till the 27th of the month. Altogether train traffic was suspended for twenty-one days. 3rd class 4th class Mail cars 262
2026-06-06 04:10:02 · Baseline
View content

6

Mines.

The only mines actually being worked at present are those at Fushun; others are in course of inspection.

Enterprises.-Working of various Railways.

When the railway was taken over, the old system was maintained till the Company had so far perfected its organization as to permit of the introduction of improvements. The actual period of working under the Company was from the 1st April to the 31st September, that is, 183 days. During the period under review the mileage open to traffic, including that carried on on the five miles between Changchun and Menchiatun, was 514 m. 14 ch.; on the Mukden-Antung line, 188 m. 56 ch.

The mileage covered by trains on the main line during this period reaches a total of 1,165,665 miles; on the Mukden-Antung line of 145,527 miles.

to

Passengers numbered 704,300, and the amount received in fares came 174,833, the busiest periods being April and May, the slackest June and July. The latter are apparently two months during which little travelling is ever done, aud in this particular year matters have been made worse by the heavy floods, which in many places caused all communication to be cut off.

Merchandize.

The amount carried was as follows :--

Ordinary merchandize

Full-car loads

Total

Tons.

11,544

468,411

479,955

£

228,715

}

7

The following Table shows the chief restoration work carried out to make good

the damage done :-

Embankments repaired

Bridges, parapets, &c., repaired

Bridges and accessories repaired în

Track repaired

débris cleared

--

2.997 tsubo,"

227

48 localities.

28 chains.

36 teubo."

This does not include ordinary repairs for the maintenance of the line. On the Antung-Mukden line maintenance of the track is an arduous task. This road was built hastily during the war for military purposes. It runs, too, through a difficult and inaccessible country full of steep gradients, while the bridges, which number 450, are only temporary structures, which, since the three years they have been standing, have for the most part become rotten. Nor are matters made easier by the frequently recurring floods, particularly those of the last summer. For instance, the bridges and embankments north of Pensihu were destroyed in this way on the 12th June last. Scarcely was the work of repairing completed, when two days of heavy rain in August, causing the rivers to rise from twelve to seventeen feet, undid all the work doue; twenty-seven bridges were washed away, and almost incalculable damage done to earthworks, culverts, &c. The result was suspension of traffic for some time, for, notwithstanding the energetic manner in which repairs were pushed forward, it was not till the last day of September that the whole line was free again.

The following Table gives statistics of the work done to repair damages of this kind:

Embankments, &c., repaired

Bridges (temporary) repaired, Culverts repaired

Covered drains repaired

Track débris cleared

relaid

"

Curs (in existence).

680 tsubo." 3,723 feet.

3 places.

13 chains.

242 "tsubo."

1 m, 32 ch.

Freight charges

The principal articles transported were as follows :-

Classification.

Quantity.

Classification.

Quantity.

Tons,

Tons.

Rice

9,685

Flour

6,661

Wheat

1,086

Beans

47,458

Bean-cake

2,862

Tobacco

1,040

Miscellaneous cereals

22,718

Paper

1,767

Salt

13,760

Limc

3,360

Sake

4,186

Dyes and chemicals

1,137

Cotton yarn

837

Cars and their materials

1,875

Silk and cotton tissues

7,335

Lumber

22,039

Earthenware

1,058

Marine products

2,969

Copper and iron goods

8,872

Provisions

3,415

Firewood

1,152

Bones (cattle)

1,024

Kerosene

1,607

Stone materials

8,574

Coal

47,618

Building materials

91,518

Fruit and vegetables

3,950

Rails

4,756

Sugar

3,010

Sleepers

15,510

There were taken over with the railway 302 locomotives, 145 passenger cars, and 4,476 goods cars, making a total of 4,923.

There are at present in the Company's possession 307 locomotives, 289 passenger cars, and 4,507 goods cars, making a total of 5,103.

Details are as follows:-

Main Line.

Classification.

Taken over in April.

Now in existence.

Increase or Decrease.

Locomotives-

Narrow gauge

6-wheeled tank, B 6

S-wheeled tender, F 2

Total

Broad guage-e

American A 10-wheeler F

::

190

30

187 30

220

217

3

Consolidation H

422

+++

སྐ༥༤༣

Total

8

+

2

8

Passenger cars-

Special bogie

3

+

8

2nd class

130

Total

145

Water tenders

10

:འ:སྐྲ ུ

15

28

+.13

128

2

100

+ 100

259

+114

12

12

:

10

Maintenance of the Line.

Considerable damage was done to the line during the past summer owing to the unusually heavy rains and to the floods therefrom resulting. In particular, on the 17th July, bridges, embankments, &c., were swept away in numbers, and for a short time communications were suspended. Again, during the heavy floods after the extraordinary rains on the 5th August, two bridges over the Fuchow River were destroyed, and parts of the neighbouring embankment swept away. On the 17th of the same month another flood took place, destroying the work but recently repaired. On this occasion the line was not restored till the 27th of the month. Altogether train traffic was suspended for twenty-one days.

3rd class 4th class

Mail cars

262

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.